ABN-AMRO Bank
Moscow, Russia
Delta Partner: ISS-Project
Start Date: May 2007
End Date: August 2007
No of Buildings: 1
No of Floors: 1
Project size: 7,000 sq. ft.
Facility / System Description:
New business centre.
1 floor for bank back-office and data center.
Delta’s system monitors leakage, temperature, humidity in
ABN-AMRO bank’s data center.
Controls of glycol temperature for precision air conditioning
units using dry coolers.
SMS alarming to maintenance staff.
MODBUS integration of Caterpillar diesel, Schneider Electric
PM800 power meters, Liebert UPSes.
DDC Architecture:
|
Product
|
Model
|
Quantity
|
Connected I/O Points
|
|
System Architecture
|
|
|
|
|
OWS / Integrated OWS
|
DOW
|
1
|
|
|
Webserver / ORCAweb
|
|
|
|
|
Area Controllers
|
DSM
|
1
|
|
|
System Controllers
|
DSC
|
|
|
|
Application Controllers
|
DAC
|
3
|
40
|
|
Field Modules
|
DFM
|
6
|
88
|
|
Access Controller
|
ASM
|
|
|
|
Access Door Controllers
|
ADM
|
|
|
|
Card Readers
|
|
|
|
|
Card Users
|
|
|
|
|
Lighting Controllers
|
DLC
|
|
|
|
ORCA Power
|
|
|
|
|
ORCA Main
|
|
|
|
3rd Party BACnet Integration
|
Type
|
Manufacturer
|
Application
|
|
MODBUS
|
Caterpillar Diesel, Liebert
|
AHU; Chiller; Monitoring of Main Power,
UPS’s, Diesel, Water Leakage, Fire Alarm
|